Zimbabwe misses digitisation deadline – $27 million required urgently to meet 2017 target

23 June 2016

According to the Herald, Obert Muganyura, the CEO of BAZ, shared this information with the Secretary in the Office of the President, Dr. Misheck Sibanda, and a delegation of BAZ and ZBC management that toured some of the stations identified for the project.

The cost of the project was set at $173 million and the money was sourced through an auction of spectrum to NetOne.

The digitisation project is now expected to be completed by mid-2017 and progress is anticipated if an injection of $27.2 million is made urgently.

This will be used for importing $10 million worth of equipment, satellite lease costs, tower replacements, securing of the 400,000 set top boxes and the digitisation of 15 sites.